Hi all,
I’m struggling with time-dating the x-axis. In connecting to estimating and forecasting a monthly model by using an ARIMA-model I run into some trouble with time dating the x-axis with I’m doing forecasting. I use the order “GRAPHFORCE”, and Shazam generates a nice plot which I can edit. But I do not find out how to time date the x-axis. The default-plot shows only a x-axis with number 1, 2, ,,,etc. Frustrating? Well, I use monthly data, and I wonder; is it possible to include some set-options in the “edit graph source” (or an alternative way) to solve the problem. Let’s say the observed data covers the period March 2003 to April 2013, and the forecast period end January 2019.
Regards, P
Ps. The option “PREDICT” does not function to store forecast-values.